The Construction Company must carry out Commissioning of the Facility in accordance with the Relevant Statutory requirement, Australian Standard or CDG and this Commissioning Schedule without limiting compliance.
This schedule describes:
in relation to the Facility prior to issue of the Certificate of Occupancy.
The standard applicable to each test, criteria or certificate is the standard described in:
If and to the extent that there is any inconsistency between the standard described in this Schedule, the Law, Health Policy, the Quality Standards, the Building Code of Australia and the manufacturer’s guidelines, the applicable standard shall be the most stringent standard.
If and to the extent that a Quality Standard permits more than one standard of testing, the relevant item shall be tested to the level specified in the Approved Drawings and Specifications or, if no level is specified, to the reasonable satisfaction of the Superintendent.
The Construction Company must operate the Facility as per the standard described in this Schedule for a continuous period of 14 days.
The Construction Company must provide monitoring equipment as appropriate (ie acceptable to an Independent Reviewer if appointed) to test the following during the 14-day period:
The monitoring equipment described must be:
The results of the ongoing testing is to be provided to the Superintendent or the Superintendent’s Representative by the Construction Company. These results may be passed onto an Independent Reviewer along with all source information, documentation and data produced by the monitoring equipment.
A Commissioning Manual is to be submitted to the Superintendent for endorsement no less than 30 business days before the construction company proposes to commence the commissioning tests by the Construction Company.
The manual, which the Construction Company must adhere to, must describe to the reasonable satisfaction of the Superintendent, a detailed and comprehensive methodology for Commissioning according to the standards set out in the Schedule. This includes:
The manual must include all tests described in the schedule and any additional commissioning tests according to the relevant Statutory requirement, Australian Standard or CDG, unless it is otherwise agreed to in writing by the Superintendent.
The manual must contain (as a minimum) the following information:
The independent Reviewer or Superintendent must specify in reasonable detail to the Construction Company why the manual is not endorsed or has only given qualified endorsement.
In relation to the facility and equipment, Appendix A: Completion Tests and B: Tests and Criteria for Equipment describes:
Not less than 30 business days before the construction company proposes to commence the commissioning tests the construction company must provide to the Superintendent:
The independent Reviewer must be satisfied that each item of equipment has been installed, calibrated (if applicable) and is operating satisfactorily according to the standards described in this schedule and the endorsed Commissioning Manual.
The Commissioning Schedule proforma describes tests, criteria and certificates in relation to the air conditioning and heating system installed in the facility.
The Tests for Criteria for Equipment proforma describes tests criteria and approvals in relation to the radiology department in the facility.
The Completion Tests proforma describes operational readiness simulations to be carried out and the relevant tests and results that must be achieved.
The Superintendent or Independent Reviewer will notify the construction company of additional simulations to test operational readiness and functionality of systems during commissioning.
The construction company must provide to the Superintendent certificates of compliance according to the Building Act 1993 and Building Regulations described in the Tests and Operational Commissioning proforma.
Not less than 30 business days before the construction company proposes to commence commissioning the construction company must submit to the Superintendent, a floor area schedule for the Hospital that contains:
The Construction Company must provide a staff schedule containing the qualifications, roster and training details of personnel to the Superintendent for approval. The schedule is to contain the personnel who have been instructed to carry out the following duties:
The construction company must demonstrate to the reasonable satisfaction of the Superintendent that has established operational procedures that record:
The construction company must demonstrate to the reasonable satisfaction of the Superintendent that it has undertaken:
The construction company must obtain an Occupancy Permit and provide this to the Superintendent, along with copies of all relevant test results and compliance certificates.
The construction company must conduct code red and code orange fire drills by calling a mock fire.
The construction company must demonstrate to the reasonable satisfaction of the Superintendent and the Metropolitan Fire Brigade (MFB or Country Fire Authority (CFA) that:
Not less than 30 business days before the Construction Company proposes to commence Commissioning the Construction Company must submit to the Superintendent a schedule that:
Each area within the Facility must be cleaned to an appropriate standard with regard to its intended purpose by the Construction Company to meet the approval of the Superintendent. In particular, operating suites and other sterile areas (including air conditioning systems) must be cleaned to the highest standard and comply with the commissioning procedures and standards described in the United Kingdom, Hospital Infection Society (HIS) Working Party report on Microbiological Commissioning and Monitoring of Operating Theatre Suites of the 4th April 2002.
The Construction Company must demonstrate to the reasonable satisfaction of the Superintendent and Hospital that:
Within one month of the completion of Commissioning according to the Schedule and the Relevant Statutory requirement, Australian Standard or CDG, the Construction Company must submit to the Superintendent an updated version of the Manual described above.
The updated Manual is to record each test carried out during Commissioning and must identify the testing criteria.
The updated Manual is to include a description of all applicable standards, methodologies, data, test results, certificates and approvals.
The Construction Company must carry out and pass the tests described in the standard Tests Table following. All installations are to be tested to the standard prescribed by the relevant authority and/or Australian Standard and/or manufacturer’s recommendation, as detailed in the Completion Tests Table.
Not less than 30 business days before the Construction Company proposes to commence the Commissioning Tests the Construction Company must provide to the Superintendent for endorsement, a detailed schedule of all tests to be undertaken and details of how and when the Construction Company proposes to carry out the testing.
The schedule must include all tests described in the Completion Tests Table and any relevant additional Commissioning Tests notified according to the Relevant Statutory requirement, Australian Standard or Capital Development Guideline (CDG), unless otherwise agreed in writing with the Superintendent.
Following completion of the relevant tests, the Construction Company must verify with the Superintendent the details of installation and the results of each completed test. The verification must be signed off by the:
The verification must confirm that installation has been constructed according to the Approved Drawings and Specifications. The Builder and the relevant Builder’s consultant(s) must sign off this part of the verification. The Builder must confirm that the installation has been constructed according to the Builder’s quality assurance program.
The Construction Company must carry out and pass the tests and satisfy the criteria described in this appendix.
The Tests and Criteria table details the tests and criteria for the Equipment related to the commissioning activities following:
Not less than 30 business days before the Construction Company proposes to commence the Commissioning Tests and the Construction Company must provide to the Superintendent a detailed schedule of all tests to be undertaken and the methodology for testing. This schedule must include (as a minimum) all tests described in the Tests and Criteria – Equipment Table (Table), which forms part of this Appendix and any Relevant Statutory requirement, Australian Standard in accordance with the Relevant Statutory requirement, Australian Standard or CDG, unless otherwise agreed in writing with the Superintendent.
Following completion of the relevant tests, the Construction Company must provide verification to the Superintendent that confirms that testing has been completed, records each test and the results of each test. The Construction Company, the Builder and the testing entity must sign off the verification.
The table also details the identity of the testing entity conducting the tests.
Not less than 30 business days before the Construction Company must submit to the Superintendent a schedule, which contains the following information:
|
Commissioning Activity |
Operational Commissioning Test |
|
Calibration and/or Biomedical Approvals |
All equipment requiring calibration and/or biomedical testing approvals, should be listed and details of testing supplied to the Superintendent, including but not limited to: Commissioning and calibration requirements including any calibration manuals, tests and standards Manufacturer's commissioning and calibration or biomedical testing requirements including any calibration manuals, tests and standards
Relevant calibration or biomedical test benchmarks: All equipment, which is to be tagged to demonstrate calibration and/or biomedical testing; and The tag number for each item of equipment. |
|
Medical Equipment |
Medical equipment that needs to be biomedically certified should be available, appropriate for intended use, installed and in working condition. This equipment may include the following items: Monitors Ventilators Image intensifiers Infusion pumps etc
Fixed equipment may include: Theatre pendant and lights Radiology equipment etc |
|
Non-medical Equipment |
Non-medical equipment (not requiring biomedical testing or calibration) should be available, appropriate for intended use, installed and in working condition. |
|
|
|
|
Category 2 Scheduled Equipment |
Category 2 scheduled equipment should be available, appropriate for intended use, installed and in working condition. |
|
|
|
|
Equipment Compliance |
All equipment and goods purchased should conform to the following standards: Australian Code of Goods Manufacturing Practice Therapeutic Goods Act Australian Standards Occupational Health and Safety Plant Regulations Any other code, law or regulation that applies to equipment purchases.
Construction Company shall provide the Superintendent with an equipment compliance statement detailing all equipment and its compliance with the required standards. |
|
Testing Entity |
Equipment checking must be conducted by appropriately qualified persons, as follows: Electrical acceptance testing (all patient equipment) by a practicing Independent Biomedical Engineer Performance testing (all essential patient equipment eg syringe pumps, infusion pumps, ventilators etc) by a biomedical engineer Area testing (operating theatres, HDU, nursery etc) by a practicing biomedical engineer Calibration and acceptance testing (Medical gases, anaesthetic, televisions, security systems, gas outlets etc) by a biomedical engineer or anaesthetist as applicable Noise testing (kitchens, workstations etc) by Ergonomist or equivalent Computer systems testing by IT supplier, installer or maintenance engineer Temperature testing (boiling water units, A/C plant) by supplier, installer, maintenance engineer as applicable Radiology equipment calibration and plant assessment by supplier/installer, performance testing by a person qualified to undertake an independent assessment of the design and siting of radiology equipment and shielding in accordance with the Health Act 1958 - Division 2AA Radiation Safety and the Health (Radiation Safety) Regulations 1994 Plant assessment of those items that have not been formally assessed by supplier according to Plant Regulations |
|
Asset Register |
Construction Company has developed an Asset register in a format that contains the required information |
|
Essential Engineering Services for Hospitals - DHS Draft Guideline July 2001 |
The Construction Company shall comply with the requirements as identified in the Draft Guidelines with respect to the provision and reporting requirements of Essential Service Infrastructure for Victorian Public Hospitals |