Gateway Review 4 confirms that the recommended tender decision is appropriate, before the contract is placed with a supplier.

This review phase provides assurances about the processes used to select a supplier.

It assesses whether:

  • The process has been well managed
  • The business needs are being met
  • Both the client and the supplier can implement and manage the proposed solution
  • The necessary processes are in place to achieve a successful outcome after contract award.

Purpose

  • Confirm the business case and benefits plan
  • Check that all necessary statutory and procedural requirements were followed throughout the procurement process
  • Confirm that the recommended contract decision is likely to deliver the specified outputs/outcomes on time, within budget and will provide value for money
  • Ensure that management controls are in place to manage the project through to completion
  • Ensure there is continuing support for the project
  • Confirm that the approved procurement strategy has been followed
  • Confirm that the department and implementation plans of both the client and the supplier/partner are achievable
  • Check that the business has prepared for developing new processes where needed and for implementing and operating new services or facilities, as well as the transition process
  • Confirm that there are plans for risk management, issue management and change management
  • Confirm that the technical implications have been addressed
  • Confirm that the proposed procurement is within the financial approvals, with adequate budget to accommodate it.

Deliverables

  • Construction – refer to Construction Insurance and Monthly Reports guidelines
  • Commissioning – refer to Commissioning of Facilities guidelines

Key Actions

  • CMB provides ERC quarterly reports on delivery against time, costs.
  • CMB monitor delivery against time, costs and quality.
  • CMB overviews construction commissioning.
  • Service Division overviews operational commissioning.

Documentation

The following documentation, where applicable, should be available before the review starts:

  • The transaction documents executed for the procurement
  • Project management documents including:
    • Strategies for managing the risks and issues, and plans and risk log showing that risks were identified and managed
    • The plan for implementing business change and plans for handling future change
    • The service management
    • The benefit management strategy, benefit management plans and responsibilities for delivery
    • The procurement strategy
    • The operational requirements and draft contract
  • Documentation detailing:
    • Confirmation that the procurement strategy approved at Gateway 3 Review has been followed
    • Confirmation that the negotiated and agreed solution remain within the original criteria
    • Confirmation that probity has been maintained throughout the procurement process
    • Realistic plans from the supplier for development and implementation
    • An evaluation report containing recommendation and justification of the selected suppliers
    • Outline project plans through to completion and plans for the next stage
    • An updated project time plan developed with the selected suppliers
    • An updated communication plan
    • Confirmation of adequate funds/budget and authority to proceed.

Key Sign Offs

  • CMB sign off quarterly reporting.
  • Any changes to endorsed scope/TEI/timeframes to be signed off by Division.
Back to top
For information relating to this page contact: Capital Management Branch, Ph: 61 3 9096 2030, capital@dhs.vic.gov.au
Site authorised by: Director, Capital Management Branch

Last Updated: 8 June, 2007
© Copyright State of Victoria | Disclaimer | Privacy statement | State Government of Victoria home | Search DHS | Download help