This guideline provides information on the general processes, which are to be followed for the commissioning of facilities where capital works have been carried out.
The commissioning process can be undertaken by a consultant/contractor or Agency/Health Service representative but should include representatives of the agency and be overseen by the Project Control Group (PCG) or Steering Committee. The Superintendent of the contract, generally the Project Manager or Principal Consultant, is responsible for ensuring that commissioning is effectively completed as programmed.
The main objectives of appropriately commissioning a facility are to:
Each project is individual and will have some issues unique to its own specific circumstances.
There are two types of Commissioning:
The participants are the:
The Superintendent is responsible to ensure coordination and that the process is undertaken in close liaison with the executive of the Agency / Service provider.
Commissioning requires that all parties agree the facilities are fit for purpose. The formal recognition of reaching this milestone is the Practical Completion certificate and the Certificate of Occupancy (or its equivalent), the release of 50% of the bank guarantee/retention fund for the project and the handing over of full responsibility to the Principal for occupation.
Building Commissioning refers to activities undertaken by representatives of the contracting parties, ie the project team leading up to the practical completion and prior to the handover of the building to the Principal for occupation.
Operational Commissioning refers to activities undertaken by the Principal leading up to and after handover to ensure staff are familiar with operating the facility before client services commence.
These include formalisation of new procedures, operational briefings, new equipment, relocation of staff and new appointments, furniture and equipment purchases, establishing asset registers and maintenance programs.
The Defects Liability period is generally 12 months. During the defects liability period the maintenance procedure should be established to include:
Prior to the end of the defects liability period, the Superintendent shall in conjunction with the Principal’s representative and the Principal Consultant/subconsultants ensure that all final defects have been addressed.
The milestones for the end of the defects period are the issue of the Final Certificate, the release of the remaining 50% of the bank guarantee / retention fund for the project and the handing over of the management of any future defects and maintenance items of the facility to the Principal.